The 2018 Street Maintenance Program has started. Work will be scheduled through the end of August. We will place message boards 2-3 days prior to starting in the area.  Expect delays during the overlay process.  For latest scheduled updates, please visit www.walker.city.

Current street listing schedule for paving:

Mullins - N and S off Three Mile - 7/28 and 7/30
Peachridge - Three Mile to the end - 7/28 and 7/30
Calann - 7/28 and 7/30
Courier Ct - 7/28 and 7/30
Orchard Ridge subdivision - 8/8 through 8/10
Bristolwood Dr - Texas to Bristol - 8/10, 8/13
Walkerwoods Ct - Waldorf N. to end - 8/10, 8/13
Pannell St. - 8/10 through 8/11

If you have any questions, please contact Public Works at (616) 791-6854.